Latest Update on Tropical Storm Gustav

Type of structure Location Duration Cost Start Date Project Type Contractor Status Parish
Retaining structures, Earthworks & Surfacing Nine Turns P.C. Road 4 months $25,598,014.45 10.11.08 Emergency Repairs - Tropical Storm Gustav S.G.Simpson Asphalting Co. Ltd. Mobilizing Clarendon
Construction of Random Rubble Wall,Spill Way & Reinstatement of roadway Graham Close, Cherry Gardens 3 months $16,200,043.20 4.11.08 Emergency Repairs - Tropical Storm Gustav Chin’s Const. Co. Ltd. Mobilizing St. Andrew
Retaining Wall & Gully Invert Reds Hills Blvd. 4 months $22,777,567.77 3.11.08 Emergency Repairs - Tropical Storm Gustav S. Green & Assoc. Co. Ltd. Mobilizing St. Andrew
Retaining wall &Gully Invert Hacienda Way 4 months $21,063,741.93 5.11.08 Emergency Repairs - Tropical Storm Gustav S.Green & Associates Ltd Started St. Andrew
Retaining Wall & Gully Invert 1.Melwood & Dillsbury Avenues 6 months $22,887,410.34 3.11.08 Emergency Repairs - Tropical Storm Gustav Y.P.Seaton & Associates Ltd. Mobilizing St. Andrew
Retaining Wall & Gully Invert Majestic Gardens Section 3 6 months $29,275,651.94 3.11.08 Emergency Road Repairs, Tropical Storm Gustav D.Bisasor & Associates Ltd. Mobilizing St. Andrew
Road Rehabilitation Queens Street 4 months $20,387,052.32 28.10.08 Emergency Road Repairs, Tropical Storm Gustav Lascar Fencing & Construction Ltd. Mobilizing Clarendon
Road Rehabilitation Mispah - Allison 6 months $27,531,528.04 6.11.08 Emergency Road Repairs, Tropical Storm Gustav Senior’s Woodwork & Construction Started Clarendon
Road Rehabilitation Bombie - Allison-Cobbla 6 months $29,985,856.11 6.11.08 Emergency Road Repairs, Tropical Storm Gustav Senior’s Woodwork & Construction Started Clarendon
Road Rehabilitation New Land Road 4 months $27,394,681.27 28.11.08 Emergency Road Repairs, Tropical Storm Lascar Fencing & Construction Ltd. Mobilizing Clarendon
Road Rehabilitation Garvey Lane, Beredale 4 months $9,931,545.84 29.10.08 Emergency Road Repairs, Tropical Storm Chin’s Equipment &Construction Co. Ltd. Mobilizing Clarendon
Road Rehabilitation Ackee Lane, Beredale 4 months $5,262,955.46 3.11.08 Emergency Road Repairs, Tropical Storm Chin’s Equipment &Construction Co. Ltd. Started Clarendon
Road Rehabilitation Oakland Crescent 3 months $7,941,821.48 23.10.08 Constituency Development Fund D.Bisasor & Assoc. Ltd. Mobilizing St.Andrew
Retaining Wall & Gully Invert Roehampton& - & Red Hills Road 5 months $35,922,842.38 3.11.08 Emergency Repairs -& Sandy Gully Network Chin’s Construction Co. Ltd. 10% St. Andrew
Retaining Wall & Gully Invert Manor View 5 months $46,934,191.67 3.11.08 Emergency Repairs Sandy Gully Network Chin’s Construction Co. Ltd. 5% St. Andrew
Retaining Wall & Gully Invert New Castle& Retaining Wall 5 months $20,208,679.43 3.11.08 Emergency Repairs Sandy Gully Network Rogers Land Development Ltd. Mobilizing St. Andrew
Retaining Wall & Gully Invert CherryGarden’s – Grant’s Pen 5 months $111,387,344.16 3.11.08 Emergency Repairs -& Sandy Gully Network Y.P.Seaton &Assoc. Ltd. 25% St. Andrew
Retaining Wall & Gully Invert Burgher Avenue 4 months $19,241,627.33 28.10.08 Emergency Repairs -& Sandy Gully Network Enviro Planners Ltd. Mobilizing St. Andrew
Retaining Wall & Gully Invert MajesticGarden’s 2 (York Street) 3 months $11,902,346.52 3.11.08 Emergency Repairs -& Sandy Gully Network R. Byers Co. Ltd. Mobilizing St. Andrew
Retaining Wall & Gully Invert Roxburgh Avenue (Arcadia) 5 months $43,494,422.73 3.11.08 Emergency Repairs -& Sandy Gully Network Lascar Fencing &Construction Co. Ltd. Started St. Andrew
Retaining Wall & Gully Invert Majestic& Gardens& 1 5 months $36,430,896.27 3.11.08 Emergency Repairs -& Sandy Gully Network D. Bisasor &Assoc. Ltd. Mobilizing St. Andrew
Retaining Wall & Gully Invert Cassia& Park 5 months $61,512,911.63 3.11.08 Emergency Repairs -& Sandy Gully Pavement &Structures Co. Ltd. 10% St. Andrew
Retaining Wall & Gully Invert Deanery Drive 4 months $17,978,966.84 28.10.08 Emergency Repairs -& Sandy Gully Enviro Planners Ltd. Mobilizing St. Andrew
River Training Mamee& River 4 months $11,944,399.06 9.10.08 Mamee River District Road& Works Project L&K Const.& Co. Ltd 30% St.Andrew
Retaining Wall &Gully Invert Mega Mart Section 1,& 2, & 3 and Upper Millsborough 5 months $59,631,446.49 3.11.08 Emergency Repairs -& Sandy Gully Surrey Paving &Aggregates Ltd Mobilizing St. Andrew
Retaining Wall &Gully Invert Beckford &Gore Dr.,& 35 Wiggan Loop, 2 Hibiscus Close, 8 Halifax Cres. 5 months $58,111,466.87 3.11.08 Emergency Repairs -& Sandy Gully Y.P.Seaton & Assoc. Ltd. Mobilizing St. Andrew
Retaining Wall &Gully Invert Lasco& -& Henkel& -& Cassia Park 5 months $58,111,466.87 3.11.08 Emergency Repairs -& Sandy Gully Hydav Const. Co. Ltd. 20% St. Andrew
Road Rehabilitation Park Lane, Mary Crane Lane 1 month $4,685,277.72 13.10.08 Constituency Dev. Fund Chin’s Const. Co. Ltd. 100% St. Andrew
Retaining Wall &Gully Invert NorwoodTerrace - Water Works 5 months $66,021,463.53 3.11.08 Emergency repairs Sandy Gully network Chin’s Const. Co. Ltd. Started St. Andrew