Lime Hall Road Retaining Wall Project - St. Ann

Background

The Green Park to St. Ann's Bay main has been the site of several major breakaways which resulted from heavy rains affecting the island overtime. These became worse during the December 2009 / January 2010 rains, thus there was an urgent need to address three of the most critical areas.

Contract and Scope of Works

A contract in the sum of J$9.875 million was awarded to New Ideas General Construction Company Limited to construct a Gabion Retaining Walls at the location in Lime Hall, St. Ann.
The details are as follows.

Location Commencement Date Duration
Lime Hall, St. Ann January 26, 2010 3 Months

Status

Wall #1 Completed
Wall #2 85%
Wall #3 92%

This project is scheduled to be completed by the end of April 2010.

Project Timeline: 
Tuesday, January 26, 2010 to Friday, April 30, 2010

FAQs