Click here for Technical Specifications for MIDP
NATIONAL WORKS AGENCY
MAJOR INFRASTRUCTURE DEVELOPMENT PROGRAMME
REPORT AT DECEMBER 31, 2017
SUMMARY OF EXPENDITURES
The Major Infrastructure Development Programme is a US$352.941 million programme jointly financed by the China Ex-Im Bank and the Government of Jamaica (GoJ). The China Exim Bank has provided 85% financing by way of a loan and the GoJ has provided the remaining 15% of the programme funds. The works under the programme are being implemented under a construction contract initially signed on January 19, 2013 between China Harbour Engineering Company Limited (CHEC) and the GoJ through the then Ministry of Transport, Works and Housing, now Ministry of Economic Growth and Job Creation with the National Works Agency being the supervisory engineer.
The programme of works is divided into three (3) components as follows;
- Major Works - This component totals US$220 million and is to be undertaken by CHEC itself.
- Medium Size Works - This component totals US$82.941 million and is to be undertaken by Jamaican contractors under sub-contracts with CHEC. This is inclusive of the Local Component projects - MIDP-LC.
- JEEP Works - This component totals US$50 million and is to be undertaken by most small Jamaican contractors under sub-contracts with CHEC. The focus of this component is minor infrastructure works including repair to gratings, sidewalks, drains, walls etc.
A review of the allocation of funds between the Major Works component, being implemented by CHEC, and the Local Component is underway.
CONTRACT AWARD UNDER MIDP
In order to ensure transparency, equity and most importantly value for money, the award of contracts under MIDP follows the GOJ procurement guidelines.
On February 7, 2017, MIDP Work Order No. 006 – Local Component – Roads, Retaining Walls and Bridges (Revised) was issued to CHEC in the amount of J$2,996,759,937.25. Subsequently in February 2017, twenty four (24) projects of Medium Size Works–Local Component (LC) were tendered.
Recommendations of tendering for the 24 LC projects were completed in the first week of March 2017. Sub-Contractors were selected by CHEC subsequently. All Sub-Contract Agreements and Commencement orders have been issued for the 24 MIDP L C projects. All works are now in progress.
On September 13, 2017, MIDP Work Order No. 007 – Local Component – Roads, Retaining Walls and Bridges was approved by MEGJC in the amount of J$4,725,061,434.56. Subsequently three (3) instructions relating to Work Order No. 007 have been issued to CHEC by NWA;
- 2017 MIDP Work Order #007-November 21, for 20 projects totalling J$1,665,577,166.00 (with CHEC Mark-up-J$1,873,774,311.75);
- 2017 MIDP Work Order # 007-November 23, for 16 projects totalling J$2,285,112,109.66 (with CHEC Mark-up J$2,570,751,123.37) and
- 2017 MIDP Work Order # 007-December 15, for 15 projects totalling J$860,777,628.60 (with CHEC Mark-up J$968,374,832.18).
In addition; of the prior MIDP projects as at August 31, 2017; a total of 57.86 km of Road Rehabilitation Works and 5 Bridges have been completed at a cost of J$1.7B, while (Lacovia) Tombstone to Gutters (length 22.40 km) is presently 99% complete with Ward River Bridge 44% complete.
With respect to the Major Works component of the programme, CHEC signed project agreements for the construction of;
- The Kupius Bridge on 16th December 2015 in the negotiated amount of US$5,537,200.87,
- Marcus Garvey Drive (between East Avenue and Pechon Street) on 4th February 2016 in the negotiated amount of US$20,499,060.20,
- Mandela Highway Improvement Project (between Six Miles Interchange and Highway 2000 Interchange) on July 22nd 2016 in the negotiated amount of US$63,997,883.63.
- Barbican Road Project (between Russell Heights Intersection and Jacks Hill Gas Station) on 9th August 2017 in the negotiated amount of US$4,351,129.58, and
- Constant Spring Road Project (between West Kings House Road and Manor Park) contract was signed on December 15, 2017 in the negotiated amount of US$19,065,913.23.
Negotiations are ongoing between MEGJC / NWA & CHEC for construction of the Mandela Highway Extension Improvement Project Phases 1 & 2. Designs and detailing work by CHEC continue on other components of the programme including Hagley Park Road and Ferris Cross to Mackfield.
Local Works
- JEEP / HOPE Minor Infrastructure Programme – JA$1,045,750M
- Civil Works – JA$4,800,000M
CHEC – Major Works
- Civil Works– JA$9,362,752M
Land Acquisition – JA$185,023M
HOPE
An amount of $866,250,000.00 was approved by MoFPS in July 2016 to fund an additional cycle of routine JEEP works across the 63 constituencies for financial year 2016/2017.
The amount to be allocated was $708,750,000.00 inclusive of CHEC fees, at $10 million per constituency for sub-contract works. The remaining $157,500,000.00 inclusive of CHEC fees was for special projects inclusive of sidewalk repairs at the discretion of the Ministry of Economic Growth and Job Creation (MEGJC) and the JEEP Secretariat.
Submissions from Sixty Three (63) Constituencies have been received with all Constituencies’ contracts signed.
For fiscal year 2016/17, the amount of J$708,153,140.60 has been certified as at March 31, 2017.
Summary of Approvals and Expenditure for JEEP 7
Original Budget |
Revised Budget |
Certified to Date |
|
1. JEEP MAIN PROJECTS |
708,750,000.00 |
|
708,153,140.60 |
2. JEEP Special Projects & Misc. |
157,500,000.00 |
|
|
Grand Total J$ |
866,250,000.00 |
|
708,153,140.60 |
HOPE / SPECIAL PROJECTS
For fiscal year 2017/18, the amount of J$736,680,108.16 has been certified as at December 31, 2017.
Summary of Approvals and Expenditure for JEEP/HOPE SPECIAL PROJECTS
Original Budget |
Revised Budget |
Certified to Date |
|
Special Projects. |
$337,000,000.00 |
|
166,572,314.58 |
HOPE Main Projects |
$708,750,000.00 |
|
570,107,793.58 |
Grand Total J$ |
$1,045,750,000.00 |
|
736,680,108.16 |
Note: Special Projects Allocation of $337,000,000.00 is comprised of a carry forward of $187,000,000.00 for works instructed in fourth quarter F/Y 2016/17 in addition to the allocation of $150,000,000.00 for F/Y 2017/18.
ROAD REHABILITATION
The table below summarises road sections completed, amounting to 57.86 kilometres. For a number of projects, a small amount of documentation remains outstanding to satisfy the requirements of the respective sub-contracts and these are being addressed.
Summary of road Sections – Sub-Contracts for Local Component of Major Infrastructure Development Programme
Control Section |
Length (Km) |
Sub-Contract Amount J$ |
Sub-Contractor |
Start Date |
Scheduled Finish Date |
% Complete |
Remarks |
May Pen – Hayes (Mineral Heights-Hayes-Dawkins Pen) |
13.70 |
268,214,308.03 |
S&G Road Surfacing |
17/6/2015 |
14/12/2015 |
100 |
Completed. |
Riley-Dias-Glasgow |
12.66 |
405,761,360.63 |
Surrey Paving & Aggregate |
17/6/2015 |
14/12/2015 |
100 |
Completed. |
Silver Spring-Santoy-Green Island |
10.59 |
186,220,350.00 |
Chin’s Construction
|
24/6/2015 |
21/12/2015 |
100 |
Completed. |
Santoy-Orange Bay |
2.41 |
46,049,062.50 |
Cemex Jamaica Limited |
30/6/2015 |
27/12/2015 |
100 |
Completed. |
Fellowship-Windsor-Seamans Valley-Moore Town |
13.00 |
249,241,916.25 |
Dwight’s Construction |
24/6/2015 |
21/12/2015 |
100 |
Completed. |
Sheffield-Silver Spring (Sheffield-Springfield) |
5.50 |
46,395,000.00 |
Alcar Construction & Haulage |
25/6/2015 |
23/12/2015 |
100 |
Completed. |
(Lacovia) Tombstone to Gutters |
22.4 |
336,150,103.09 |
S&G Road Surfacing |
4/7/2016 |
31/3/2017 |
99 |
Work in progress – (V/O) NWC pipeline installation practically completed |
In addition, the Contractor (CHEC) has expressed its intention to carry out the rehabilitation works on the 11 kilometre road section from Chovey to Highgate and has been given the design and estimate for these works. The NWC by way of letter dated November 26, 2015 has advised that the NWA should include the pipe works in the contract. As a result, CHEC is preparing the costing for undertaking these waterworks.
The Mandeville via Swaby’s Hope to Spur Tree in Manchester requires additional design work and land acquisition and is being progressed. CHEC will be implementing the improvement works along 5 kilometre of the Mandeville to Spur Tree road section.
BRIDGES – Sub Contracts
Six (6) bridges were earmarked for implementation of which four (4) are completed with two (2) ongoing.
Details are included in the table below:
Summary of Bridges – Sub-Contracts for Local Component of Major Infrastructure Development Programme
Bridge |
Parish |
Sub-Contract Amount J$ |
Sub-Contractor |
Start Date |
Scheduled Finish Date |
% Complete |
Remarks |
Silent Hill |
Clarendon |
24,730,087.50 |
Alcar Construction & Haulage |
25/6/2015 |
23/10/2015 |
100 |
Completed. |
Jacobs River 1 and 2 (Lime Bush) |
Portland |
23,861,812.50 |
Cemex Jamaica Limited |
30/6/2015 |
28/10/2015 |
100 |
Completed. |
Latium Bridge |
St. James |
25,207,762.50 |
Cemex Jamaica Limited |
30/6/2015 |
28/10/2015 |
100 |
Completed. |
Ward River Bridge |
St. Thomas |
64,783,884.38 |
Chins Construction Limited |
1/3/2016 |
1/9/2016 |
44 |
Work in progress, after JPS delays. |
Rentcombe Bridge |
St. Catherine |
39,145,117.50 |
Surrey Paving & Aggregate |
15/2/2016 |
15/6/2016 |
100 |
Completed. |
Bridges & Road Works – Major Works Component
Summary of Bridges & Road Projects – Contracts for Major Works Component of Major Infrastructure Development Programme
Bridge / Road |
Parish |
Contract Amount US$ |
Contractor |
Start Date |
Scheduled Finish Date |
% Complete |
Remarks |
Kupius |
Clarendon |
5,537,200.87 |
C H E C |
11/1/2016 |
11/3/2017 |
100 |
Completed. |
Marcus Garvey Drive |
Kingston |
20,499,060.20 |
C H E C |
1/3/2016 |
1/5/2017 |
100 |
Completed. |
Mandela Highway |
St. Andrew & St. Catherine |
63,997,883.63 |
C H E C |
17/8/2016 |
31/8/2018 |
79 |
Work in progress. |
Barbican Road |
St. Andrew |
4,351,129.58 |
C H E C |
25/8/2017 |
21/2/2018 |
35 |
Work in Progress |
LOCAL COMPONENT (LC) – MIDP – WORK ORDER NO.: 006 |
|||||||
Project Name |
Parish |
Sub-Contract Amount J$ |
Sub-Contractor |
Start Date |
Scheduled Finish Date |
% Complete |
REMARKS |
Mona Road |
St Andrew |
76,439,090.00 |
Asphaltic Concrete Ent. |
20/3/2017 |
20/9/2017 |
100 |
Completed |
Back Bush |
St Andrew |
63,400,000.00 |
Y.P. Seaton & Assoc. |
20/3/2017 |
20/9/2017 |
100 |
Completed |
Essex Hall W/Rural St Andrew |
St Andrew |
58,391,000.00 |
Alcar Construction |
20/3/2017 |
20/9/2017 |
100 |
90% with V/O Works |
Irish Town Road |
St Andrew |
269,089,750.00 |
Asphaltic Concrete Ent. |
20/3/2017 |
20/9/2017 |
85 |
V/O works approved |
St Andrew Urban Roads |
St Andrew |
226,387,390.00 |
General Paving Co. |
20/3/2017 |
20/9/2017 |
100 |
Work in progress |
Sandy Gully Repairs |
St Andrew |
151,160,350.00 |
Dwight’s Construction |
20/3/2017 |
20/9/2017 |
100 |
Completed |
Tranquillity – Bangor Ridge |
Portland |
56,648,000.00 |
Dwight’s Construction |
20/3/2017 |
20/9/2017 |
80 |
Work in progress |
Chepstow – Ythanside |
Portland |
32,509,000.00 |
Dwight’s Construction |
20/3/2017 |
20/9/2017 |
80 |
Work in progress |
Retreat – Lambkin Hill |
St Mary |
115,665,680.00 |
Dwight’s Construction |
20/3/2017 |
20/9/2017 |
80 |
Work in progress |
Ocho Rios Bypass |
St Ann |
101,492,650.00 |
Alcar Construction |
20/3/2017 |
20/9/2017 |
100 |
Completed |
Dumbarton Box Culvert |
St Ann |
21,139,407.00 |
S & G Roads Surfacing |
20/3/2017 |
20/9/2017 |
100 |
Completed |
Riverside Park, Ensom City |
St Catherine |
103,574,920.00 |
Construction Solutions |
20/3/2017 |
20/9/2017 |
100 |
Completed |
Succaba South East |
St Catherine |
44,709,100.00 |
Construction Solutions |
20/3/2017 |
20/9/2017 |
100 |
Completed |
Begonia Crescent |
St Catherine |
48,507,000.00 |
Dwight’s Construction |
20/3/2017 |
20/9/2017 |
100 |
Completed |
Federal Road |
St Catherine |
97,287,250.00 |
Construction Solutions |
20/3/2017 |
20/9/2017 |
100 |
Completed |
Albert Town – Lorrimers |
Trelawny |
236,960,160.00 |
Surrey Paving & Agg. |
20/3/2017 |
20/9/2017 |
100 |
Completed |
Sign – Virgin Valley |
St James |
191,511,227.00 |
Y. P. Seaton & Assoc. |
20/3/2017 |
20/9/2017 |
100 |
Completed |
Guava Walk Road |
St James |
60,233,250.00 |
Dwight’s Construction |
20/3/2017 |
20/9/2017 |
97 |
Work in progress |
Flower Hill Roads |
St James |
128,051,420.00 |
S & G Roads Surfacing |
20/3/2017 |
20/9/2017 |
100 |
Completed |
Lethe Copse |
Hanover |
85,636,334.00 |
Y. P. Seaton & Assoc. |
20/3/2017 |
20/9/2017 |
100 |
Completed |
Middle Quarters, New Market |
St Elizabeth |
285,000,601.50 |
Build-Rite Construction |
20/3/2017 |
20/9/2017 |
40 |
Work in progress |
Lancelot Mitchell Town Portland Cottage Crossing |
Clarendon |
239,800,000.00 |
Build-Rite Construction |
20/3/2017 |
20/9/2017 |
60 |
Work in progress |
Toll Gate – Rest |
Clarendon |
176,573,250.00 |
Construction Solutions |
20/3/2017 |
20/9/2017 |
85 |
Work in progress |
Sedburg – Clandon |
Manchester |
91,995,100.00 |
S & G Roads Surfacing |
20/3/2017 |
20/9/2017 |
100 |
Completed |
TOTAL |
|
2,962,560,889.50 |
|
|
|
|
|
LOCAL COMPONENT (LC) – MIDP – WORK ORDER NO.: 007 – (November 21, 2017) |
|||||||
|
|
|
|
|
|
|
|
Project Name |
Parish |
Sub-Contract Amount J$ |
Sub-Contractor |
Start Date |
Scheduled Finish Date |
% Complete |
REMARKS |
Felicity Road – Norwood |
St James |
48,263,500.00 |
Surrey Paving |
21/11/2017 |
21/5/2018 |
0 |
|
Flower Hill – Tornado Heights |
St James |
46,504,200.00 |
Chin’s Const. |
21/11/2017 |
21/5/2018 |
0 |
|
Flower Hill Road |
St James |
7,586,000.00 |
Chin’s Const. |
21/11/2017 |
21/5/2018 |
0 |
|
Rose Mount – Rose Heights |
St James |
9,123,000.00 |
Chin’s Const. |
21/11/2017 |
21/5/2018 |
0 |
|
Valencia Drive, |
St James |
16,303,000.00 |
Chin’s Const. |
21/11/2017 |
21/5/2018 |
0 |
|
Sun Valley – Norwood (Johnson Hill) |
St James |
25,908,000.00 |
Chin’s Const. |
21/11/2017 |
21/5/2018 |
0 |
|
Stewart Town to Lorrimers (Comfort Hall – Wirefence) |
Trelawny |
186,915,300.00 |
Surrey Paving |
21/11/2017 |
21/5/2018 |
0 |
|
Smithfield Main Road |
Hanover |
32,271,900.00 |
Chin’s Const. |
21/11/2017 |
21/5/2018 |
0 |
|
White Shop – Banana Ground |
Clarendon |
94,048,360.00 |
S & G Road Surf. |
21/11/2017 |
21/5/2018 |
0 |
|
Macknie – Douglas Castle |
Clarendon |
75,541,600.00 |
S & G Road Surf. |
21/11/2017 |
21/5/2018 |
0 |
|
Springfield – Pisgah |
St Elizabeth |
85,938,798.00 |
S & G Road Surf. |
21/11/2017 |
21/5/2018 |
0 |
|
Coleyville Main Road |
Manchester |
104,810,103.00 |
S & G Road Surf. |
21/11/2017 |
21/5/2018 |
0 |
|
Mark Post – Mile Gully |
Manchester |
54,552,680.00 |
S & G Road Surf. |
21/11/2017 |
21/5/2018 |
0 |
|
Bowers Gully Bridge |
St Catherine |
78,780,000.00 |
Surrey Paving |
21/11/2017 |
21/5/2018 |
0 |
|
Brethren Town |
St Catherine |
49,165,400.00 |
Dwight’s Construction |
21/11/2017 |
21/5/2018 |
0 |
|
Gutters – Bushy Park |
St Catherine |
81,841,500.00 |
Construction Solutions |
21/11/2017 |
21/5/2018 |
0 |
|
Wakefield – Savannah |
St Catherine |
160,893,400.00 |
Dwight’s Construction |
21/11/2017 |
21/5/2018 |
0 |
|
Naggo Head Road |
St Catherine |
249,781,825.00 |
Dwight’s Construction |
21/11/2017 |
21/5/2018 |
0 |
|
Fairfield Road |
St Catherine |
159,626,500.00 |
Construction Solutions |
21/11/2017 |
21/5/2018 |
0 |
|
Fearon Close, Hibiscus Drive, Mayflower Drive, Mitchell Close, etal |
St Catherine |
97,722,100.00 |
Construction Solutions |
21/11/2017 |
21/5/2018 |
0 |
|
GRAND TOTAL |
|
1,665,577,166.00 |
|
|
|
|
|
LOCAL COMPONENT (LC) – MIDP – WORK ORDER NO.: 007 – (November 23, 2017) |
|||||||
Project Name |
Parish |
Sub-Contract Amount J$ |
Sub-Contractor |
Start Date |
Scheduled Finish Date |
% Complete |
REMARKS |
Windward Road (Mountain View – Rockfort) |
St Andrew |
143,110,000.00 |
Chin’s Construction |
28/11/2017 |
28/5/2018 |
0 |
|
Clermont – Whitehall |
St Mary |
96,874,300.00 |
Dwight’s Construction |
28/11/2017 |
28/5/2018 |
0 |
|
Mount Salem – Upper King Street |
St James |
37,166,000.00 |
Chin’s Construction |
28/11/2017 |
28/5/2018 |
0 |
|
Cocoa Piece – Alexandria |
Clarendon |
213,310,900.00 |
Build-Rite Construction |
28/11/2017 |
28/5/2018 |
0 |
|
Palmers Cross – Main Street, May Pen |
Clarendon |
98,461,005.75 |
Construction Solutions Limited |
28/11/2017 |
28/5/2018 |
0 |
|
Dawkins Pen – Lionel Town – Bustamante – Race Course |
Clarendon |
244,000,500.00 |
Build-Rite Construction |
28/11/2017 |
28/5/2018 |
0 |
|
Lititz – Comma Pen |
St Elizabeth |
173,000,900.00 |
Build-Rite Construction |
28/11/2017 |
28/5/2018 |
0 |
|
Mountainside – Fullerswood – Watchwell Main Road |
St Elizabeth |
195,200,000.00 |
Build-Rite Construction |
28/11/2017 |
28/5/2018 |
0 |
|
White House Road |
St Catherine |
62,756,500.00 |
Dwight’s Construction |
28/11/2017 |
28/5/2018 |
0 |
|
Hamwalk – Bagbie, |
St Catherine |
182,551,923.80 |
Construction Solutions |
28/11/2017 |
28/5/2018 |
0 |
|
Mansfield Ave & Madrid Ave |
St Catherine |
40,048,571.08 |
Construction Solutions |
28/11/2017 |
28/5/2018 |
0 |
|
Rockstone |
St Catherine |
46,232,112.16 |
Construction Solutions |
28/11/2017 |
28/5/2018 |
0 |
|
Windsor Ave |
St Catherine |
14,852,431.10 |
Construction Solutions |
28/11/2017 |
28/5/2018 |
0 |
|
Windsor Road & Duncan’s Pen |
St Catherine |
44,446,010.77 |
Construction Solutions |
28/11/2017 |
28/5/2018 |
0 |
|
Woodhall – Belfield |
St Catherine |
221,159,945.00 |
Y. P. Seaton & Associates |
28/11/2017 |
28/5/2018 |
0 |
|
Sherman Terrace/Welside Lane, Marlie Mount |
St Catherine |
45,318,100.00 |
Dwight’s Construction |
28/11/2017 |
28/5/2018 |
0 |
|
GRAND TOTAL |
|
2,285,112,109.66 |
|
|
|
|
|
LOCAL COMPONENT (LC) – MIDP – WORK ORDER NO.: 007 – (December 15, 2017) |
|||||||
Project Name |
Parish |
Sub-Contract Amount J$ |
Sub-Contractor |
Start Date |
Scheduled Finish Date |
% Complete |
REMARKS |
4th Street |
St. James |
9,005,000.00 |
Surrey Paving and Aggregates Limited |
|
|
0 |
|
6th Street |
St. James |
7,724,250.00 |
Surrey Paving and Aggregates Limited |
|
|
0 |
|
Bogue Hill Road |
St. James |
39,147,500.00 |
Surrey Paving and Aggregates Limited |
|
|
0 |
|
Home Hill – Ironshore (Quebec Ave) |
St. James |
59,667,000.00 |
Surrey Paving and Aggregated Limited |
|
|
0 |
|
Guava Ridge – Content Gap |
St. Andrew |
146,000,000.00 |
Alcar Construction |
|
|
0 |
|
Coakley – Mt. Airy (Brandon Hill) |
St. Andrew |
43,260,500.00 |
Alcar Construction |
|
|
0 |
|
Port Morant Main Road – Airy Castle (4km) |
St. Thomas |
95,440,000.00 |
Alcar Construction |
|
|
0 |
|
Yallahs – Lowe Mountain |
St. Thomas |
195,100,500.00 |
Alcar Construction |
|
|
0 |
|
Duncan’s Pen Box Culvert |
St. Catherine |
16,829,181.60 |
Construction Solutions Limited |
|
|
0 |
|
Tranquillity |
Portland |
29,600,000.00 |
Build-Rite Construction |
|
|
0 |
|
Sherlock Crescent, Dickens Ave, Champlin Ave & Flamstead Ave |
St. Andrew |
40,541,033.50 |
Chin’s Construction |
|
|
0 |
|
Armour Height East Oakridge East |
St. Andrew |
48,888,950.00 |
Chin’s Construction |
|
|
0 |
|
Armour Heights West – Oakridge West |
St. Andrew |
54,350,890.00 |
Chin’s Construction |
|
|
0 |
|
Irish Town Road (Papine – Redlight) Phase 2 |
St. Andrew |
26,887,520.00 |
Chin’s Construction |
|
|
0 |
|
Michigan Close |
St. Andrew |
48,335,303.50 |
Chin’s Construction |
|
|
0 |
|
GRAND TOTAL |
|
860,777,628.60 |
|
|
|
|
|
MAJOR ROAD RECONSTRUCTION WORKS
Kupius Bridge:
The project agreement for the construction of Kupius Bridge (in Clarendon) was signed on 16th December 2015 in a negotiated amount of US$5,537,200.87 between Ministry of Transport, Works & Housing and China Harbour Engineering Company Limited the Main Contractor.
The scope of works comprised the construction of a two span 67 meters long pre-stressed concrete bridge on reinforced concrete bored piles and abutments, 12.51 meter wide to accommodate 2 lanes of traffic and 2 sidewalks. The contract period was set at 14 months with contractual start date at January 11, 2016. Construction works are practically complete.
Marcus Garvey Drive:
Negotiation for construction of the Marcus Garvey Drive (between East Avenue and Pechon Street) project was concluded on 22 January 2016 in a negotiated amount of US$20,499,060.20 between Ministry of Transport, Works & Housing and China Harbour Engineering Company Limited the Main Contractor. The contract was signed by the Government of Jamaica and China Harbour Engineering Company on 4th February 2016.
The scope of works comprised the extension of a six lane carriageway, two major box culverts, drainage improvements and other works inclusive of sidewalks and traffic signals. The contract period was set at 12 months with contractual start date at March 1, 2016. Construction works are practically complete.
Mandela Highway Improvement Project:
Negotiation for construction of the Mandela Highway Improvement Project (between Six Miles Interchange and Highway 2000 Interchange) project was concluded on 27th May 2016 in the negotiated amount of US$63,997,883.63 between the Ministry of Economic Growth and Job Creation and China Harbour Engineering Company Limited the Main Contractor.
The contract was signed by the Government of Jamaica and China Harbour Engineering Company on July 22nd 2016.
The scope of works comprises extensive soil treatment, construction of 3.5km six lane corridor with a two lane overpass bridge two new three lane bridges at Fresh River, a two lane service road adjacent to the main corridor to facilitate the development of Caymanas Estate and upgrading of the Six Miles Interchange. Construction works are on schedule.
Barbican Road Improvement Project
Negotiation for construction of the Barbican Road Improvement Project (between Russell Heights Intersection and Jacks Hill Gas Station) was first agreed on May 12, 2017 in a negotiated amount of US$4,462,679.90; however this was sent back for further review and was revised on July 13, 2017 in a negotiated amount of USD$4,351,129.58 between the Ministry of Economic Growth and Job Creation and China Harbour Engineering Company Limited the Main Contractor. The contract was signed by the Government of Jamaica and China Harbour Engineering Company on 9th August 2017.
The scope of works comprises 1.09 km of a four lane corridor comprised of Road Construction Works – Demolition and Site clearance, Earthworks, Roads and Pavement, Culverts, Traffic Facilities and Lighting and Communication Facilities and extension of the Bustamante Bridge in addition to major drainage works.
Constant Spring Road Improvement Project
Negotiation for construction of the Constant Spring Road Improvement Project (between West Kings House Road and Manor Park) was concluded on September 11, 2017 in a negotiated amount of US$19,065,913.23; between the Ministry of Economic Growth and Job Creation and China Harbour Engineering Company Limited the Main Contractor. The contract is approved by the cabinet with the signing date by the Government of Jamaica and China Harbour Engineering Company to be arranged.
The scope of works is 4.2 km of a four lane corridor comprised of Road Construction Works – Pavement Works, Site clearance, Earthworks, Culverts, Traffic Facilities and Lighting & Communication Facilities with a two-lane Overpass Bridge at Manor Park in addition to major drainage works.
Mandela Highway Extension Works, Phase 1 and 2:
Negotiation for construction of the Mandela Highway Extension Improvement Project Phase 1 & 2 (between the Highway 2000 Interchange and Jose Marti Roundabout) is in the final stages of conclusion between the Ministry of Economic Growth and Job Creation and China Harbour Engineering Company Limited the Main Contractor.
The scope of works includes but is not limited to the construction of eleven and one half (11 1/2) kilometres of road embankment and asphalt concrete pavements storm water highway drainage ditches and swales with five (5) reinforced concrete bridges. The improvement works will result in increasing the carriageway from two lanes to three lanes in either direction.
Designs are progressing by CHEC for major road improvement works on the following roads:
- Hagley Park Road – Kingston & St. Andrew
- Ferris Cross to Mackfield – Westmoreland
The Contractor’s design team has had frequent meetings with the NWA regarding confirmation of the Employer’s requirement and specifications for use in informing the designs. The Contractor is currently undertaking a number of surveys including Hagley Park Road.
Within the Corporate Area, it is planned to implement major intersection improvement works at Waterloo/Hope Roads commencing in the next financial year, for which the designs are well advanced.
ANCILLARY WORKS
The Government of Jamaica has allocated funds for critical needs inclusive but not limited to water and sewage pipeline repair / installation works on selected MIDP projects, to prevent rehabilitated road works from deterioration due to external factors unrelated to the road construction activities such as leaking water/sewage mains.
The National Water Commission (NWC) is responsible for the technical specifications and approval of estimates for water and sewage pipeline ancillary works.
Funds are paid to CHEC for disbursement as per existing MIDP arrangements inclusive of mark-up.
A listing of current Ancillary Works is shown in the table below:
Sub-Contracts – Ancillary Works – Major Infrastructure Development Programme
Control Section |
Parish |
Sub-Contract Amount J$ |
Expenditure J$ |
Sub-Contractor |
% Complete |
Middle Quarters New Market |
St. Elizabeth |
161,883,427.50 |
86,734,552.50 |
Build-Rite Construction Co. Ltd. |
60 |
Lancelot Mitchell Town – Portland Cottage Crossing |
Clarendon |
101,529,983.86 |
54,866,644.14 |
Build-Rite Construction Co. Ltd. |
55 |
Toll Gate – Rest |
Clarendon |
89,973,922.50 |
77,854,725.00 |
Construction Solutions Ltd. |
99 |
Barbican Road Improvement Project |
St. Andrew |
148,047,356.25 |
42,318,618.75 |
Surrey Paving & Aggregate Co. Ltd. |
65 |
|
Total |
501,434,690.11 |
261,774,540.39 |
|
|
66
THE PROGRAMME OF ACTIVITIES FOR THE MIDP
The MIDP is designed to improve some 431km of road along the network together with 27 bridges.
Subject to the rate of progress of the works and the budget for fiscal year 2017/18 additional road sections and bridges may be instructed to proceed to the implementation stage.