Hot Mix Patching starts in St. Elizabeth

Date Published: 
11 Dec 2014

The National Works Agency (NWA) is advising motorists and pedestrians that the Agency has commenced a programme of Hot Mix patching along sections of roadways in St. Elizabeth.

Patching will be carried out along the Tombstone to Gutters, Scotts Cove to Luana and Luana to Tombstone corridors. The works are scheduled to last for three weeks and should be completed by December 30, 2014.

Community Relations Officer of the NWA’s South Region, Howard Hendriks says that the patching of these roadways will be done by one of  the NWA’s Force Account Teams at a cost of two million dollars. Mr. Hendriks says that approximately 700 square metres of patching will be undertaken along these road sections.

The NWA is advising motorists and pedestrians to obey posted warning and directional signs and the instructions of flag persons while work is in progress.